Which of the following best defines a work breakdown structure (WBS)?a.) List of project tasks that define the critical pathb.) List of resources and tasks in a projectc.) List of broken down project deliverables
C.
Option (c) List of broken down project deliverables best defines a Work Breakdown Structure (WBS). It is a hierarchical decomposition of project deliverables into smaller, more manageable components of work. In other words, it is a visual and detailed representation of project scope that outlines all the tasks required to complete a project from start to finish.
The WBS breaks down the project into smaller, more manageable pieces, helping project managers to effectively plan, organize, and complete project tasks. It allows the team to track project progress, easily identify the critical path, and manage resources efficiently.
Overall, a WBS is an essential project management tool that provides a clear understanding of the project scope and helps in planning and executing project tasks in a structured and organized manner.
More Answers:
Boost User Engagement and Efficiency with Math Prototyping: Try it First Before You Build for Perfectionthe Role of Modular Design in Engineering and Design Processes
UML: The Standard Language for Effective Software Design and Collaboration